Project Information
Project Details: Baker McKenzie – Level 4, 100 New Bridge Street
Contract Value: £650K
Duration: 5 months: November 2018 – March 2019
Works Overview:
CAT B fit Out
Comms Room Rationalisation – simultaneous refurbishment and decommission of 2 separate comms rooms into 1
CAT B Fit Out – Works Description
MECHANICAL POWER REQUIREMENTS:
NEW LIGHTING SCHEME THROUGHOUT:
NEW SPECIALIST LIGHTING:
Unique Project Issue – Comms Room Rationalisation